EEAgentur.chEEAgentur.ch
EFFEL
The programmeEFFEL for companies
Measures
Standardised measuresNon-standardised measuresFunding check
FAQAbout usContactFunding checkRegister as a utility
ImprintPrivacySitemap
EEAgenturEEAgentur
The programmeEFFEL for companies
Standardised measuresNon-standardised measuresFunding check
FAQAbout usContact
Funding check
EEAgentur

EEAgentur is a service of Energieagentur St.Gallen. We make efficiency measures eligible for the EFFEL programme and match them with electricity suppliers.

energieagentur-sg.ch ↗bfe.admin.ch ↗

Programme

  • The programme
  • EFFEL for companies

Measures

  • Standardised measures
  • Non-standardised measures
  • Funding check
  • Register as a utility

Agency

  • FAQ
  • About us
  • Contact

Legal

  • Imprint
  • Privacy
  • Sitemap
© 2026 Energieagentur St.GallenEFFEL · Efficiency gains through electricity suppliers · Art. 46b EnG
  1. Home
  2. Standardized Measures
  3. Pumps
  4. PU-01b

SFOE standard catalogue · Pumps · Version 2.0

Addition of VFD for Water Pump Systems with Constant Speed up to 75 kW

The goal is to estimate the electricity savings triggered by adding a frequency converter (VFD) for water pump systems with constant speed up to 75 kW with demand analysis. This measure is relevant when analyses have confirmed that the required flow rate is constant, but the current value is too high. The desired flow rate is achieved with reduced pressure. The savings are related to the reduction in flow rate and pressure.

At a glance

PU-01b

Type
Retrofit
Version
2.0
Example A
no example in the catalogue
Proofs
3 documents
Start funding check for PU-01b
  • Requirements
  • Proofs
  • Calculation basics
  • Downloads

Requirements

Only measures that meet the requirements of the Energy Ordinance (SR 730.01; EnV) can be credited. The additional requirements for the technical characteristics and for the implementation of the measure are set out in Table 1.

TechnologyThis measure applies to water pumps including motors with a rated power Pnom (at the shaft) of up to 75 kW that fall within the scope of Annexes 2.9 and 2.7 EnEV. Adding a frequency converter is only permitted if the pump and the motor are newer than: Pnom ≤ 5.5 kW 8 years 5.5 < Pnom ≤ 20 kW 10 years Pnom > 20 kW 14 years
Energy efficiencyThe new components of the drive system must meet at least the following limit values according to EnEV: Frequency converter Class IE2
The efficiency of the pump before and after installing the frequency converter must be within a range of ± 5% of the pump's optimal efficiency.
Energy analysis / needs analysisAn energy analysis must be carried out to review the needs and sizing of the pump system. This analysis must show the electricity consumption and the efficiency of the system before and after implementation and be carried out by a person qualified according to ISO 14414.
SizingThe total installed rated power of the new system must be less than or equal to the total installed rated power of the old system
ImplementationThe replacement and commissioning of the new system must be carried out by a qualified specialist or company.

Proof of compliance

Compliance with the requirements must be demonstrated by the following documents. The documents listed in Table 2 are an integral part of the proof of measure implementation.

  1. 1.The needs analysis (PDF format) carried out when resizing the new installation
  2. 2.Invoice documents (PDF, PNG or JPEG format)
  3. 3.Photos (PDF, JPEG or PNG format) of the old and the new installation, including the rating plates of the devices (pumps and motors)
Calculation basics: symbols, units and formulasNot needed for the review, useful for recalculating▾

Symbols, Terms and Units

SymbolDescriptionUnit
Eannual electricity consumptionkWh/a
ΔEecocumulative electricity savingskWh
fFactor—
NsStandard effective durationa
ΔpDifferential pressure at pump connectionskPa
QFlow ratem³/h
tannual operating hoursh/a
η_CFEfficiency of frequency converter—
η_PPump efficiency—
η_MMotor efficiency—

Calculation Formulas

Stromverbrauch der aktuellen Pumpe

Eold = Ė_alt × t

The electricity consumption of the current pump is calculated based on the measurement of the electrical power consumption by the system.

Stromverbrauch nach der Sanierung

Enew = (Δpneu × Qneu × t) / (η_P,neu × η_M,neu × η_CF,neu)

The electricity consumption after renovation is calculated based on the actually required flow rate and the additional losses due to the frequency converter.

Wirkungsgrad des Frequenzumrichters

η_CF,x = 0.79 + 0.22 × (1 - 1/log₁₀(40 × Pm,nom,x))

The additional losses caused by a frequency converter can be expressed depending on the rated power of the motor.

Downloads

Documentation (PDF)Complete technical documentation including calculation basisDownload DOC
Excel Calculator (XLSX)Interactive calculation tool for savingsDownload PRO

Previous measure

← PU-01a · Simple Replacement of Water Pump Systems with Constant Speed up to 75 kW

Next measure

PU-01c · Resizing of Water Pump Systems with Constant Speed up to 75 kW →

Other measures in Pumps

PU-01aSimple Replacement of Water Pump Systems with Constant Speed up to 75 kWPU-01cResizing of Water Pump Systems with Constant Speed up to 75 kW

Part of the EFFEL programme

Standardised measures are one of two measure types in the EFFEL programme (efficiency improvements by electricity suppliers, Art. 46b EnG). They follow a predefined SFOE catalogue with fixed savings values.